L
LJH
Hi
Can someone help me? I am new to MS Project, and managing my first project,
but the duration of tasks is giving me some strange numbers For example...
Duration
Task 1 37.94 days
Task a 1 day
Task b 1 day
Task 2 6.31 days
Task a 1 day
Task b 1 day
Task c 0.5 day
What have I done to cause this, and how can I fix it without project
automatically recalculating all of the other dates?
Many thanks in advance
Lisa
Can someone help me? I am new to MS Project, and managing my first project,
but the duration of tasks is giving me some strange numbers For example...
Duration
Task 1 37.94 days
Task a 1 day
Task b 1 day
Task 2 6.31 days
Task a 1 day
Task b 1 day
Task c 0.5 day
What have I done to cause this, and how can I fix it without project
automatically recalculating all of the other dates?
Many thanks in advance
Lisa