Task durations displaying in calendar view - Project 07 Standard

A

ARBrock

I need to be able to take the task durations off of the bars in calendar view
so it only displays the task name. I'm slightly stuck because it seems to be
a default view that I cannot get off.
 
M

Mike Glen

Hi ARBrock,

Welcome to this Microsoft Project newsgroup :)

Try Format/Bar Styles/... select the bar type and delete the Duration from
the Text field at the bottom of the dialog.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 