I am using MS Project 2003 Standard Edition
If I have working day of 8 hours and create a task with a duration of 7
hours, it starts and finishes on the same day, as I would expect. If I
change the duration to 7.1 hours, it finishes on the next working day, which
I would NOT expect. Any ideas as to why it should do this?