S
smithersbig
I have a task with a task calander assigned to it, with work days
specified from Oct. 31 to Dec. 31st. But the early start for this task
is listed as June 8; which is defined as a non working day for the task
calander. Is there any way to make the early start date and Gnatt
chart show Oct. 31st? I feel that MS Project is handling the
working/non working days in its calculations of finish dates, but it
shows a start date that is defined as a non working day. Can anyone
help?
specified from Oct. 31 to Dec. 31st. But the early start for this task
is listed as June 8; which is defined as a non working day for the task
calander. Is there any way to make the early start date and Gnatt
chart show Oct. 31st? I feel that MS Project is handling the
working/non working days in its calculations of finish dates, but it
shows a start date that is defined as a non working day. Can anyone
help?