Task Level Reporting

S

Scott E

What is the best way to report on the task level? We have multiple
users who report their time on a single task. I would like to get the
detailed information out (total hours and cost for each resource on
the task).

Should we create a macro to copy the "task name" and "business charge
back code" to the resource enterprise outline code (view the field in
resource usage) on every "save" of the project plan. Then, can we
view the information in a portfolio analyzer view?

Thanks,
Scott E
 