D
David Wanless
I'm using Project Standard 2003.
I have a 300 task project file. On many tasks, I have allocated myself
(David Wanless) as resource at a rate of 80%. However, many of these now
have a work value of 0hrs. How can a task of duration 5 days have a resource
allocated at 80% for 0hrs?
Note that other resources are allocated to the same task. Some of their
work values are also wrong, although not 0.
If I create a new task with all the same resources allocated, it calculates
my Work value as 30h, matching the 80% of my time.
Is there any way I can get Project to recalculate the Work values for all
resources allocated to all tasks on the basis of their Duration and the Unit
allocations?
Any other suggestions? I desperately do not want to have to recreate every
task in the project.
David.
I have a 300 task project file. On many tasks, I have allocated myself
(David Wanless) as resource at a rate of 80%. However, many of these now
have a work value of 0hrs. How can a task of duration 5 days have a resource
allocated at 80% for 0hrs?
Note that other resources are allocated to the same task. Some of their
work values are also wrong, although not 0.
If I create a new task with all the same resources allocated, it calculates
my Work value as 30h, matching the 80% of my time.
Is there any way I can get Project to recalculate the Work values for all
resources allocated to all tasks on the basis of their Duration and the Unit
allocations?
Any other suggestions? I desperately do not want to have to recreate every
task in the project.
David.