S
Shelley
I'm trying to change task times and i get a dialog box asking to link
tasks, so I did (even though the tasks aren't dependant upon each
other). After linking tasks, Microsoft Project would allow me to
change the start time and end time of the task. However, once I
changed them, saved and closed, Project would revert back to the time
displayed before. How do I fix this?
Also, I am using a file from 2002 and I updated all of the dates to
2003. However, the Gantt chart still shows all of 2002 and I have to
scroll all the way to the right to get to my tasks in 2003. How do I
fix that? I already tried to create a new baseline calendar, but that
didn't seem to work either.
Help!!
Thanks!
Shelley
tasks, so I did (even though the tasks aren't dependant upon each
other). After linking tasks, Microsoft Project would allow me to
change the start time and end time of the task. However, once I
changed them, saved and closed, Project would revert back to the time
displayed before. How do I fix this?
Also, I am using a file from 2002 and I updated all of the dates to
2003. However, the Gantt chart still shows all of 2002 and I have to
scroll all the way to the right to get to my tasks in 2003. How do I
fix that? I already tried to create a new baseline calendar, but that
didn't seem to work either.
Help!!
Thanks!
Shelley