Task Usage view at a Summary Task Level

C

Crumbs Chief

Hi,

I have a project with several levels of detail, on the top level I have three
summary tasks ST1 to ST3, these have summary tasks below them etc. At the
lowest level are the actual tasks with resources assigned to them and then
work allocated.

What I would like to see for each summary task (ST) is what resources are
working how many hours. Without alll the detail of what tasks they are doing
i.e.

ST1
John 3
Jessica 5
Adam 8

ST2
John 10
Adam 2
Eva 4

ST3
Jessica 5
Eva 4
Tom 2

It is essentially the Task Usage view at a Summary Task Level.

Any ideas on how to obtain such information?

Cheers
 
R

Rod Gill

You can collapse summary tasks in the task Usage view to see total hours per
time period only, but you can see the resources as they are not assigned to
the summary task, but the sub-task.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top