C
Claus33
I had to implement a number of changes into an existing project plan (arround
1000 tasks). After number od optimizations, I noticed that a number of tasks
were shifted to later dates. All of them are succesors of other tasks and
their constraint is "start as soon as possible". I can not recognize any
reason, why these tasks do not start directly after their predeccesors. Their
are no constraints like "Must start at" etc. and there are no values
calculated (e.g. "work done" etc.).
I found only a trick to move these tasks to the "as soon as
possible"-position:
First I have to change their status to ""Must start at" and directly after
this setting I have to set them back to "Start as soon as possible". After
this "trick", these tasks are starting at the desiered dates ("as early as
possible").
How van I avoid such cumbersome corrections?
Regards
Claus
1000 tasks). After number od optimizations, I noticed that a number of tasks
were shifted to later dates. All of them are succesors of other tasks and
their constraint is "start as soon as possible". I can not recognize any
reason, why these tasks do not start directly after their predeccesors. Their
are no constraints like "Must start at" etc. and there are no values
calculated (e.g. "work done" etc.).
I found only a trick to move these tasks to the "as soon as
possible"-position:
First I have to change their status to ""Must start at" and directly after
this setting I have to set them back to "Start as soon as possible". After
this "trick", these tasks are starting at the desiered dates ("as early as
possible").
How van I avoid such cumbersome corrections?
Regards
Claus