Hi,

We are running Project Server 2003,

Whilst updating the timesheet views today, I have noticed there are
some tasks showing in PWA, which don't exist within MSP anymore.

How would I go about removing these?

Thanks in advance
Suzannne
 
M

Mike

Suzanne,

In PWA you can simply highlight the task (just click the empty cell
before the task name) and then click the "Hide" button at the top.
This effectively deletes it from the PWA timesheet. The only way it
will return is if the plan owner reassigns and republishes the task.

Another way is that the plan owner can remove all remaining work for
the resource for that task and republish assignments.

Good luck.
Mike
 