Tasks rolled up under summary tasks.

S

schemr

hi,
i am trying to make the Summary Task display a red stop light based on the
tasks under it (the rest of the tasks are indented below the summary task and
the summary task has a "+" for expansion. now how would i make it so that if
there are more than three red stop lights under the summary task( ie if 3 or
more of the subtasks have a red light) that the summary task has a red light,
else shows a green light. hope the question is understandable. thank you.

schemr
 
S

schemr

PS. im askin this question b/c my summary bar isnt acting according to the
fomula of the field.
 
J

JackD

Right click on the column header.
Choose "Customize fields"
In the dialog box that shows up check the settings for "Calculation for task
and group summary rows". If it is not set to "use formula" then that is your
problem.
 