..the lights

G

GregL

Sorry to keep beating this horse, but how do I get the
stoplights, which I've already setup, formula and
everything in my Project Plans to actually show up in the
Project Center under "Projects"?

I have admin rights but can't crack the 'how-to' code just
yet.

Thanks again.
 
D

Dale Howard [MVP]

GregL --

As the Project Server administrator, you need to add the custom fields to
one or more Project views in PWA. In addition, you need to instruct your
project managers to "push" the values in these fields to PWA by clicking
Collaborate - Publish - All Information or Collaborate - Publish - Project
Plan. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 

Ask a Question

Want to reply to this thread or ask your own question?