Time Constraint Symbol on every task ...

G

Greggy

For some reason every single task has a time contraint symbol. Is this
normal? I didn't intend to do that, if not normal, how do I remove?

Thanks,
Greg
 
G

Gérard Ducouret

Hello Greg,

You probably entered directly a Start Date or a Finish date on each task.
To remove the constraints:
Double Click on the task row, in the Task Information dialog, Click the
Advanced tab, in the Constraint Type drop down list, select as Soon As
Possible.

Another way to do that if there is a large number of constraints :
Insert the column "Constraint type" in any table.
Select the new column,
Ctrl + Del
Then remove this column : Del

Gérard Ducouret
 
G

Greggy

Awesome. Thank you for your help. :)

Gérard Ducouret said:
Hello Greg,

You probably entered directly a Start Date or a Finish date on each task.
To remove the constraints:
Double Click on the task row, in the Task Information dialog, Click the
Advanced tab, in the Constraint Type drop down list, select as Soon As
Possible.

Another way to do that if there is a large number of constraints :
Insert the column "Constraint type" in any table.
Select the new column,
Ctrl + Del
Then remove this column : Del

Gérard Ducouret
 
G

Greggy

Hmmm... seems to be changing all the dates. I have a date I want the task
to be on, and when I change it to "as sson as possible' the dates changes to
the same date as the one above it.
 
G

Gérard Ducouret

Does this task has a logical predecessor ? May be you have to correct it in
the "Predecessors" column.
If this task has all the logical predecessors and don't fall on the date you
want, may be it deserves a date constraint....

Gérard Ducouret
 
J

Jan De Messemaeker

Hi,

If you want to set the date yourself, you ARE constraining the task, aren't
you?
So Project tells you that YOU constrained the task.
What's wrong with that?
 
S

Steve House [Project MVP]

That's what it is supposed to do. You don't tell Project the schedule you
want. It tells you the schedule you can HAVE that gets the project done as
efficiently as possible given what needs to be done, the order things need
to be done, and the availability of the resources who are able to do it.
The only time you supply start and finish dates is when there are specific
factors that constrain the task against being freely scheduled - the vendor
of some parts required to do X won't deliver before the 1st of November so
you enter task X with a start of 01 Nov, indicating that for some reason it
simply cannot take place before that date.

If you had infinite resources and no task required something that another
task produces as its input, the most efficient schedule would indeed start
all of the tasks on the same day and run them in parallel. But some tasks
must happen before others by the nature of the process - you have to put up
the walls before you can install the roof - and you don't have unlimited
resources - you only have so many carpenters and Joe Carpenter can only work
on one thing at a time. The time schedule where tasks occur in a sequence
is a consequence of the impact of those factors that limit how much can be
going on at once but you won't see it in the schedule until you have input
all the information the calculations are based on - durations, task links,
resource schedules, and resource assignments.
 
G

Greggy

I wasn't sure if therer wasn't anything wrong with it. I just didn't know
and was wondering if it was supposed to be like that.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top