Lars Aurdal
Hi,
for each task in my project I need to display the START and STOP time of the
task in days from the start of the total project. I'll introduce two new
columns, one called Start from T0 and another called Stop from T0. So if my
total project starts on the 1st of january and I have a task that starts on
the 10th of January and ends on the 15th then I would like these two columns
to read 10 and 15 respectively.
Possible?
Best wishes
Lars