Time from start of project

L

Lars Aurdal

Hi,

for each task in my project I need to display the START and STOP time of the
task in days from the start of the total project. I'll introduce two new
columns, one called Start from T0 and another called Stop from T0. So if my
total project starts on the 1st of january and I have a task that starts on
the 10th of January and ends on the 15th then I would like these two columns
to read 10 and 15 respectively.

Possible?

Best wishes

Lars
 
J

Jan De Messemaeker

Hi Lars,

Yes, perfectly possible if you have Project 2000 or +
You have to customize two duration fields using a formula with the DateDiff
function (if you want to show lapsed days) or the project datediff function
if you want to show working days.

HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top