M
major.tal
Hi all,
We started trying to do our high level planning with MS Project.
Our granularity is Months, and while I know how to configure the GUI to
work with months I don't know how to set the engine itself to work this
way.
I set "Work is entered in Months" and "Schedule is entered in Months".
I set the timescales of the different views to show months.
I have also set the leveling resolution.
The problem is everything is converted to days within the engine!
I start a task January 1st with a duration of 2 months.
It will not end by the end of February! There is always some annoying
skew.
I Even if I get it right, once the task is moved to a different month
it will change again since the months have a different amount of work
days (which I don't care about at this stage!)
Can I somehow configure the software to work with Months as the basic
element?
Crazy idea: should I change my calendar so that all months have exactly
20 work days?
Thanks in advance,
Tal.
We started trying to do our high level planning with MS Project.
Our granularity is Months, and while I know how to configure the GUI to
work with months I don't know how to set the engine itself to work this
way.
I set "Work is entered in Months" and "Schedule is entered in Months".
I set the timescales of the different views to show months.
I have also set the leveling resolution.
The problem is everything is converted to days within the engine!
I start a task January 1st with a duration of 2 months.
It will not end by the end of February! There is always some annoying
skew.
I Even if I get it right, once the task is moved to a different month
it will change again since the months have a different amount of work
days (which I don't care about at this stage!)
Can I somehow configure the software to work with Months as the basic
element?
Crazy idea: should I change my calendar so that all months have exactly
20 work days?
Thanks in advance,
Tal.