I am Ph.D. student (cancer cell biology) and am new to Project 2007.
The issue I am having is that every task is a fixed duration and not
effort driven. Most tasks in a lab are you start something and then
you have to wait. Therefore, a task might require 3 days to complete
because of the wait times. These wait times make it possible to
overlap multiple tasks in any given day. The question is: Is there a
wait to uncouple the length of time a task requires from the resource
time devoted to it. For example, a procedure takes 3 days (72 hours)
but it only requires about 10 total hours of my time spread over those
three days. How do I set Project to model this?
Thanks,
Adrian.
The issue I am having is that every task is a fixed duration and not
effort driven. Most tasks in a lab are you start something and then
you have to wait. Therefore, a task might require 3 days to complete
because of the wait times. These wait times make it possible to
overlap multiple tasks in any given day. The question is: Is there a
wait to uncouple the length of time a task requires from the resource
time devoted to it. For example, a procedure takes 3 days (72 hours)
but it only requires about 10 total hours of my time spread over those
three days. How do I set Project to model this?
Thanks,
Adrian.