Time Scale: getting Quarters to line up with day of project start

S

Steve VC at NGC

How can I set one of the time scales to display quarter increments from the
start of the project? The way it works now it's slightly off by a month or so.

Thanks,
steve
 
R

Rod Gill

If you want a quarter scale with Q1, Q2 format you need to set the project's
start date to the first day of a quarter, then edit the label of the
timescale (Format, Timescale).
 
S

Steve VC and NGC

Rod,
I need Q1 to start on May 18th for example. Can projects do that?
It would be nice to see 3 month increments from the start of the project
since that is how it works in this particular case. (program starts when
contract is signed).
thanks for additional help
steve
 