Current view in timesheet entry does not appear to be working.
Timesheet entry has 2 views for dispalying tasks: current and all. I
believe the current view should show all task that:
- not complete and
- were either scheudled to start or have started or will start within
the number of days specified by the administrator (I have set this to 1 day)
But what happens, is that the developer can see all of his tasks...the
current filter does not appear to be working. What am I doing wrong?
MS Project Server 2003