M
MAT
Hi
i have such a Problem:
I open a project (which is in Server) with MS Project 2003.
Then I change the actual work of a task for a Ressource.
Then I publisch the project again.
Now the Ressource can not see the actual work that I changed.
The days im Timesheet (which) I changed are empty.
The Ressource sees just the actuael work that he had with PWA changed.
But in Projct Center I see that the "% Comlited" is correct..
Any idea?
Thanks...
i have such a Problem:
I open a project (which is in Server) with MS Project 2003.
Then I change the actual work of a task for a Ressource.
Then I publisch the project again.
Now the Ressource can not see the actual work that I changed.
The days im Timesheet (which) I changed are empty.
The Ressource sees just the actuael work that he had with PWA changed.
But in Projct Center I see that the "% Comlited" is correct..
Any idea?
Thanks...