U
Uttkarsh Kalia
Hi,
I would like to understand whether "% work complete" and "Actual Hours" are
inter-related or not. For example: For a Task1, Work = 16 hours, % Complete =
50%.
Does this mean that "Actual Hours" = 8 hours ?
In a practical scenario, a person may work for 8 hours on the above Task1,
but the task need not be 50% complete.
Could you please tell me whether " % Complete" & "Actual Hours" can be
considered as unrelated attributes in PWA 2003?
I would like to understand whether "% work complete" and "Actual Hours" are
inter-related or not. For example: For a Task1, Work = 16 hours, % Complete =
50%.
Does this mean that "Actual Hours" = 8 hours ?
In a practical scenario, a person may work for 8 hours on the above Task1,
but the task need not be 50% complete.
Could you please tell me whether " % Complete" & "Actual Hours" can be
considered as unrelated attributes in PWA 2003?