P
Pete C
Hi, when I run a 'To Do List' report, filtered by resource, then while the
'Work' column is displayed, only the total work for that task is shown. What
I am needing to do is, for each task, to show only that particular resource's
work.
If relevant, am using Project Professional 2002 (10.0.2002.0502).
Any ideas please?
'Work' column is displayed, only the total work for that task is shown. What
I am needing to do is, for each task, to show only that particular resource's
work.
If relevant, am using Project Professional 2002 (10.0.2002.0502).
Any ideas please?