3
3326ubb
Hi,
Using MSP2002 professional.
Created Master project by inserting individual project.
Levelling required to be done with a typical constraint on number of
resources.
The activities should be pushed or rescheduled if number of resources (
across all sub-projects ) exceed 40. Because the platform on which these
activities will be carried can not accomodate more than 40 persons of
all vendors together.
Can this be done with available levelling options ? If at all it is
possible, which activities will be pushed ?
Help/advice will be appreciated.
Using MSP2002 professional.
Created Master project by inserting individual project.
Levelling required to be done with a typical constraint on number of
resources.
The activities should be pushed or rescheduled if number of resources (
across all sub-projects ) exceed 40. Because the platform on which these
activities will be carried can not accomodate more than 40 persons of
all vendors together.
Can this be done with available levelling options ? If at all it is
possible, which activities will be pushed ?
Help/advice will be appreciated.