Can I flip the Scheduled vs Actual bars - Scheduled on top/Actual on the
bottom?
Pete
I hope you want to do this in Tracking gantt view. I suggest you copy
the Tracking gantt view, before doing the below steps.
How to copy the Tracking gatt?
a. Choose View | More views ...
b. Select Tracking Gantt view and select copy ...
c. Give a new name in "View Definition" window.
How to customize the bar styles?
a. Use Format | Bar styles
b. Replace the values "Start" to "Actual Start" and "Finish" to
"Actual Finish" in From and To columns
c. Replace the values "Baseline Start" to "Start" and "Baseline
Finish" to "Finish" in From and To columns
Let us know if this helps