Tracking Graph Gnatt

T

tshad

On the Tracking Graph for the Gnatt Chart, why are some lines Red and some
Blue?

Thanks,

Tom
 
J

Jim Aksel

Task that are red are on the critical path to project completion.
The critical path is the chain of tasks that determine the minimum duration
of the project and have 0 slack (or float). These are the tasks that must
start and finish on time for the proejct schedule to finish when indicated.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
T

tshad

Jim Aksel said:
Task that are red are on the critical path to project completion.
The critical path is the chain of tasks that determine the minimum
duration
of the project and have 0 slack (or float). These are the tasks that must
start and finish on time for the proejct schedule to finish when
indicated.

That was what I was looking for.

I would rate this, but I am just looking at it in my outlook explorer and
there is no place to rate.

Thanks,

Tom
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top