Task that are red are on the critical path to project completion.
The critical path is the chain of tasks that determine the minimum duration
of the project and have 0 slack (or float). These are the tasks that must
start and finish on time for the proejct schedule to finish when indicated.
--
If this post was helpful, please consider rating it.
Jim
Visit
http://project.mvps.org/ for FAQs and more information