H
Helge Svee
I have one summary activity which is summary of two activities.
Activity 1: duration = 390 days
Activity 2: duration = 30 days linked to act 1 with start-start and lag 110
days.
When I update these activities I get a result I mean must be wrong.
What I do: I report progress at act 1 with these parameters actual
start=planned start(baseline start), act dur = 105 days and remaining dur =
285 days. Act 2 has not started and according to baseline this is right.
What I get at the summary act is:
Actual dur = 97,5 days and remaining dur = 292,5 days.
I have calculated what MSP does( (105/420)*390) = 97,5 days as act dur. In
my head this is WRONG. When I report that the activity have progress in 105
day, then its wrong that MSP calculates the act dur to 97,5 days.
IS IT A WAY AROUND THIS PROBLEM?
Activity 1: duration = 390 days
Activity 2: duration = 30 days linked to act 1 with start-start and lag 110
days.
When I update these activities I get a result I mean must be wrong.
What I do: I report progress at act 1 with these parameters actual
start=planned start(baseline start), act dur = 105 days and remaining dur =
285 days. Act 2 has not started and according to baseline this is right.
What I get at the summary act is:
Actual dur = 97,5 days and remaining dur = 292,5 days.
I have calculated what MSP does( (105/420)*390) = 97,5 days as act dur. In
my head this is WRONG. When I report that the activity have progress in 105
day, then its wrong that MSP calculates the act dur to 97,5 days.
IS IT A WAY AROUND THIS PROBLEM?