T
Té
I have switched to the tracking table on Microsoft Project. I have entered
100% in the complete field for two tasks. My act. dur is 5.28 days. I dont
understand how it is 5.28 days when they act duration for one task is 1 day
and the other task is 4 days. The remaining duration is 51.72 days. Where
are these decimals coming from? I read somewhere the actual duration =
duration * percent complete, but I'm coming up with 3.55. My percent
complete is 71. I did 5 * .71.
100% in the complete field for two tasks. My act. dur is 5.28 days. I dont
understand how it is 5.28 days when they act duration for one task is 1 day
and the other task is 4 days. The remaining duration is 51.72 days. Where
are these decimals coming from? I read somewhere the actual duration =
duration * percent complete, but I'm coming up with 3.55. My percent
complete is 71. I did 5 * .71.