A
Andres
Hi!
I have the following problem, which I think I explain
better with an example:
I planned the duration of a task, say 10 days, using
resource "A" full-time. While executing, say at day 5, I
realized that the task is not progressing as planned and
that it will require another resource to finish the task
on time. Therefore, I assigned the resource ("B"). When I
did the latter, I wanted to change work and costs for the
remaining 5 days (future). However, changes affected
previous five days(past),as well, which ocurred with only
resource "A" assigned.
Does anyone knows how to avoid this problem???
Thanks for your help!!!
A
I have the following problem, which I think I explain
better with an example:
I planned the duration of a task, say 10 days, using
resource "A" full-time. While executing, say at day 5, I
realized that the task is not progressing as planned and
that it will require another resource to finish the task
on time. Therefore, I assigned the resource ("B"). When I
did the latter, I wanted to change work and costs for the
remaining 5 days (future). However, changes affected
previous five days(past),as well, which ocurred with only
resource "A" assigned.
Does anyone knows how to avoid this problem???
Thanks for your help!!!
A