M
Mauricio@BVFG
Hello team,
I have a task which is assigned resources from the resource pool and global
resources. For this global resources I have already changed the Workgroup to
none so that I don't receive spooler errors when publishing the file to the
server.
Project users are able to submit their timesheet for the task; project
manager can approve their timesheet and the task % complete increases
accordingly, but what about the global resources? If I try modifying manually
the taks % complete I receive a message stating the task is probably
unsynched, which is true given the fact global resources are not submitting a
timesheet.
How do I manage this scenario to show both Project Server users and global
resources work reflected in the task % complete?
Thanks in advance
Mauricio
I have a task which is assigned resources from the resource pool and global
resources. For this global resources I have already changed the Workgroup to
none so that I don't receive spooler errors when publishing the file to the
server.
Project users are able to submit their timesheet for the task; project
manager can approve their timesheet and the task % complete increases
accordingly, but what about the global resources? If I try modifying manually
the taks % complete I receive a message stating the task is probably
unsynched, which is true given the fact global resources are not submitting a
timesheet.
How do I manage this scenario to show both Project Server users and global
resources work reflected in the task % complete?
Thanks in advance
Mauricio