trevor
I am getting ready to track the progress of a project. I wasnt sure if
project incorporates more than just percentage complete. what happens if i
change the start or finish date or duration. will that be compared against
the bassline?
project incorporates more than just percentage complete. what happens if i
change the start or finish date or duration. will that be compared against
the bassline?