Trailing dots on calendar

A

Anita

When I add holidays to an individuals calendar it adds extra days to any
tasks affected by the holiday. When I take the holiday out and set the days
back to what they were there is a trail of dotted lines on the gannt chart -
I have been told that this is a bug in the software.

Is there any work around or patch for this and why does it do it?

Many thanks

Anita
 
J

JulieS

Hi Anita,

Is the task type fixed duration? (Split the screen from the Gantt chart and
check the task form at the bottom.) If so, this is not a bug in the software.
The task's duration is extended by the resource's holiday. When you remove
the holiday, the expanded duration does not automatically contract (it's
fixed). The trailing dots indicate the task's finish date is after the end of
the work for the resource. Set the task type back to fixed units, and the
trailing should disappear. You can then set the task type back to fixed
duration.

Hope this helps. Let us know how you get along.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top