elazzaro
I have a task which can be done, at earliest, six weeks before a milestone,
and at latest two weeks before the milestone. Using ASAP, I expect it to be
scheduled six weeks before; but it's not late unless it slips past two weeks
before. It has no relationship to any other task besides the milestone.
How do I represent this?
and at latest two weeks before the milestone. Using ASAP, I expect it to be
scheduled six weeks before; but it's not late unless it slips past two weeks
before. It has no relationship to any other task besides the milestone.
How do I represent this?