Two shifts

M

Mike Gerrits

I am working with a project schedule requiring two (10 hr) shifts per day.
How can I set the Gantt chart to show a separate area for each shift??
 
M

Mike Glen

Hi Mike,

Welcome to this Microsoft Project newsgroup :)

You can't do for both shifts. The best I can offer is in Format/Timescale
and select the Nonworking time tab where you can select one of the shift
calendars.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question