K
KT
Hello Everyone!!
This is a U-D-W question. I have two resources assigned to a task (review
report) which takes 2 hours. Hence both the resources have to work two hours
each. I tried setting up several option like fixed units, fixed duration and
fixed work but in vain. I understand that its a fixed work task, but when I
set the task as fixed work (2 hours), the work is shared between the two
resourses as one hour each. Can somebody tell what's wrong I am procedure and
help me out?!! Thanks for all your help.
This is a U-D-W question. I have two resources assigned to a task (review
report) which takes 2 hours. Hence both the resources have to work two hours
each. I tried setting up several option like fixed units, fixed duration and
fixed work but in vain. I understand that its a fixed work task, but when I
set the task as fixed work (2 hours), the work is shared between the two
resourses as one hour each. Can somebody tell what's wrong I am procedure and
help me out?!! Thanks for all your help.