B
Bob Inwater
I have what I think is a unique Project Management and MS Project problem.
I have 3 sets of tasks that each are populated at different levels of detail
in one MS Project File.
The first phase of the project represents 43% of the days to be consumed
(SUM of the all durations) but accounts for only 15 % of the cost. The second
and third phases have much less detail (line items) so there value in terms
of total percent complete is under weighted. The workforce for each phase is
different. Consumption of hours calculates the % complete per take but since
the resources in each phase are not measured the same the Total Project %
complete is way off.
MS Project does not seem to have a way to address this. Ideas?
I have 3 sets of tasks that each are populated at different levels of detail
in one MS Project File.
The first phase of the project represents 43% of the days to be consumed
(SUM of the all durations) but accounts for only 15 % of the cost. The second
and third phases have much less detail (line items) so there value in terms
of total percent complete is under weighted. The workforce for each phase is
different. Consumption of hours calculates the % complete per take but since
the resources in each phase are not measured the same the Total Project %
complete is way off.
MS Project does not seem to have a way to address this. Ideas?