J
Jeff
I have a large master project file, where I have tried to link specific
milestone tasks in this large file to identical tasks in smaller
projects--this is necessary so I can have one large project file but also
have individual project presentations at various meetings. It appears that
when I update the master file the start/finish dates and durations in the
smaller project files also change, but I would also like the %Complete to
update in the smaller project files whenever a change is made to the large
file. Is this possible?
milestone tasks in this large file to identical tasks in smaller
projects--this is necessary so I can have one large project file but also
have individual project presentations at various meetings. It appears that
when I update the master file the start/finish dates and durations in the
smaller project files also change, but I would also like the %Complete to
update in the smaller project files whenever a change is made to the large
file. Is this possible?