URGENT Resource Problem - Please Help :-)

E

Elle

The problem...

Task A = 8 man days of work, 5 for 'PMO' - 1 for 'PM' - 2 for 'Other'

I have lots of 'Other' resource and 1 'PM'...so no problem BUT I only have 2
'PMO' for 5 man days of work

By my calculations the duration should come out as 2.5 days

But project has set the duration at 1.6 days? and said that PMO is over
allocated...

....but it wouldn't be if it said 2.5 days duration

Thanks for you help
 
J

JulieS

Hi Elle,

If you wish the task to take 2.5 days -- enter the task and set is as fixed
duration, non-effort driven. Assign the PMO and enter 40 hours of work.
Project will calculate 200% assignment units. Assign the PM at 8 hours of
work (40% assignment units) and assign Other at 16 hours of work (80%
assignment units.)

I hope this helps.

Julie
Project MVP
 
M

Mike Glen

Hi Elle,

Welcome to this Microsoft Project newsgroup :)

If you plan for 2 PMO to do 5 days of work, the Duration will be 2.5 days.
You need to enter PMO at 200% to use 2 of them, which will give your the 2.5
days you want.

You might like to have a look at my free series for beginners on Microsoft
Project in the TechTrax ezine, particularly #5 on Resources, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 