The problem...
Task A = 8 man days of work, 5 for 'PMO' - 1 for 'PM' - 2 for 'Other'
I have lots of 'Other' resource and 1 'PM'...so no problem BUT I only have 2
'PMO' for 5 man days of work
By my calculations the duration should come out as 2.5 days
But project has set the duration at 1.6 days? and said that PMO is over
allocated...
....but it wouldn't be if it said 2.5 days duration
Thanks for you help