M
Mike Jones
I'm sure this is a basic question...yes, I need to get a book.
We generally estimate the actual hours of work a task will take, so I
think I want to use effort-driven calculation. So I want to enter the
hours of Work (right?). If I'm understanding, Duration is calendar
span time, so if I have an 8 hour task, but the resource is available
50% of the time, the duration is 2 days. Am I on the right track?
Then I'd like the durations, start and end dates calculated for me.
What I'm seeing is a little odd. I'm seeing "1 day?" for duration in
many of the tasks, and then even thought the work is 1/2 hour, it
consumes the whole day. The resource is only actually scheduled for a
1/2 hour, even though 8 hours are available. We don't allow such
slacking!
There must be something basic that I'm missing here. How do I make
Project level resources so that all available time is effectively
used?
Thanks.
We generally estimate the actual hours of work a task will take, so I
think I want to use effort-driven calculation. So I want to enter the
hours of Work (right?). If I'm understanding, Duration is calendar
span time, so if I have an 8 hour task, but the resource is available
50% of the time, the duration is 2 days. Am I on the right track?
Then I'd like the durations, start and end dates calculated for me.
What I'm seeing is a little odd. I'm seeing "1 day?" for duration in
many of the tasks, and then even thought the work is 1/2 hour, it
consumes the whole day. The resource is only actually scheduled for a
1/2 hour, even though 8 hours are available. We don't allow such
slacking!
There must be something basic that I'm missing here. How do I make
Project level resources so that all available time is effectively
used?
Thanks.