Hi joooles,
Next time, try posting on the microsoft.public.project.server newsgroup (forum). Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm
Mike Glen
Project MVP
Hello joooles,
It seems it's a bad pratice. Please see the posts I noticed several month
ago:
Gérard Ducouret
------------------------------------
If we assign a Cost resource to a task (as the only one resource on that
task) and then we enter some % Complete, Project Pro 2007 calculates the
Actual Cost correctly.
If we assign a Cost resource to a task besides a Work resource, and then we
enter some % Complete, Project Pro 2007 does not calculate any Actual Cost
for the Cost resource.
Answer 1:
Because of this and because Cost Resources inappropriately affect duration,
you need to define a separate task for cost resources in order to use them
effectively.
Answer 2: Eric M. Zenz (MSFT) <
[email protected]>
% Complete functions differently when the assignment only contains a cost
resource vs. a mixture of cost and work or material. This is by design.
We can only infer that the % complete refers to the completion of
expenditure of money if the only assignment is a cost assignment. When the
assignments are mixed, we must assume or infer that the task % complete
applies to work progress and not cost progress for legacy reasons. The
workaround you describe is the suggested best practice use.