G
Gigi
Hello,
We use Project 2003 as a timekeeping tool instead of a scheduling tool, it
is mandated.
Our situation is we have hundreds of individual projects that span a 12
month fiscal year, and work is done sporadically throughout the year until
the "project" is completed. It may be completed in one month or take the
entire twelve months. The projects are assigned hours to complete, from 8
hours to 1500 hours and they will have varying numbers of resources. The
resources apply work toward a project sporadically.
I am having trouble with deciding which task type to use, as well as
duration. The projects are measured in hours. I am obviously doing
something wrong now, because the actual hours worked (protected) are being
moved to the project start instead of the date they were actually worked. I
have the "start on actual date" box checked as opposed to the "start on
Project date" box so I'm not sure where I have gone wrong.
Should I be measuring the projects' duration in months instead of hours?
And which task type would be best suited for this timekeeping scenario?
Thank you so much in advance, I really appreciate all of your help. I have
learned a lot from this board although... obviously not enough!
THANK YOU.
We use Project 2003 as a timekeeping tool instead of a scheduling tool, it
is mandated.
Our situation is we have hundreds of individual projects that span a 12
month fiscal year, and work is done sporadically throughout the year until
the "project" is completed. It may be completed in one month or take the
entire twelve months. The projects are assigned hours to complete, from 8
hours to 1500 hours and they will have varying numbers of resources. The
resources apply work toward a project sporadically.
I am having trouble with deciding which task type to use, as well as
duration. The projects are measured in hours. I am obviously doing
something wrong now, because the actual hours worked (protected) are being
moved to the project start instead of the date they were actually worked. I
have the "start on actual date" box checked as opposed to the "start on
Project date" box so I'm not sure where I have gone wrong.
Should I be measuring the projects' duration in months instead of hours?
And which task type would be best suited for this timekeeping scenario?
Thank you so much in advance, I really appreciate all of your help. I have
learned a lot from this board although... obviously not enough!
THANK YOU.