HI. We do not currently have an enterprise solution available to us so I am
trying to save my project files in a single Access DB so that we can have the
kind of reporting we want. I have noticed that I am unable to see anything
in the WBS field in the Task table (in access). Any idea why this is so?
Thanks
 
D

DavidC

Hi,
Do not not why, and I had not noticed this before. However simillar data is
available in the field Task_Outline_Level if that is of some help.
 