I am trying to use the Resource Availability table to set up a team of 8
people by setting the team (Developers) with 800% max allocation. According
to MSP-2003 help, I should be able to do this. Help says:
"For example, you have a resource named Engineers, representing three
individual engineers on your team. You can enter the maximum units for
Engineers as 300 percent. You can schedule all three engineers for full-time
work at one time without the Engineers resource being overallocated"
But when I assign this team to a task (for high level planning purposes) to
see how long the task will take to complete, it does not set the duration as
I expected, it kept the duration as if it was only 1 resource working at 100%
a not 8 resources at 100%. What am I missing.
people by setting the team (Developers) with 800% max allocation. According
to MSP-2003 help, I should be able to do this. Help says:
"For example, you have a resource named Engineers, representing three
individual engineers on your team. You can enter the maximum units for
Engineers as 300 percent. You can schedule all three engineers for full-time
work at one time without the Engineers resource being overallocated"
But when I assign this team to a task (for high level planning purposes) to
see how long the task will take to complete, it does not set the duration as
I expected, it kept the duration as if it was only 1 resource working at 100%
a not 8 resources at 100%. What am I missing.