Team resource work

V

Vadim Malyshev

Hello All,

Project Server 2007 question:

I have created the following resources:
1. Real man, team: System Analytics
2. System Analytics, team: System Analytics, team pool

After that I have created project with two tasks:
1. One task, duration: 1 month, resource: Real man
2. Second task, duration: 1 month, resource: System Analytics

I want to indicate that my project requires hiring one System Analytic.

But:
1. The resource availability report on Project 2007 Server doesn’t indicate
any availability or other activity on "System Analytics" resource.
2. The report cube doesn’t have any work values on it.

I am confused :-( Please help me!

Vadim Malyshev
 
M

Mike Glen

Hi Vadim,

Try posting on the microsoft.public.project.server newsgroup. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
M

Mike Glen

Hi Vadim,

I'm afraid that list is years out of date as 2 and 3 were removed 3 to 5
years ago. The current ones are in the FAQ I referenced.

Mike Glen
Project MVP
 