V
Vadim Malyshev
Hello All,
Project Server 2007 question:
I have created the following resources:
1. Real man, team: System Analytics
2. System Analytics, team: System Analytics, team pool
After that I have created project with two tasks:
1. One task, duration: 1 month, resource: Real man
2. Second task, duration: 1 month, resource: System Analytics
I want to indicate that my project requires hiring one System Analytic.
But:
1. The resource availability report on Project 2007 Server doesn’t indicate
any availability or other activity on "System Analytics" resource.
2. The report cube doesn’t have any work values on it.
I am confused :-( Please help me!
Vadim Malyshev
Project Server 2007 question:
I have created the following resources:
1. Real man, team: System Analytics
2. System Analytics, team: System Analytics, team pool
After that I have created project with two tasks:
1. One task, duration: 1 month, resource: Real man
2. Second task, duration: 1 month, resource: System Analytics
I want to indicate that my project requires hiring one System Analytic.
But:
1. The resource availability report on Project 2007 Server doesn’t indicate
any availability or other activity on "System Analytics" resource.
2. The report cube doesn’t have any work values on it.
I am confused :-( Please help me!
Vadim Malyshev