Hello,

my problem is: i have to make a project, only for the holidays.
has anyone any idee how can i do this ??? sorry but i m new in those
things...

in the menu view, at resource usage i would like to see the holiday for
my team, holidays - red and work time - yellow .is this posible ?

Please help!

Thanks
armo
 
C

Catfish Hunter

I am confused at what you want so I'll take a stab at it.
Go to view Gant Chart and add task for each person taking holiday.
Assign each new task to a calendar. You may need to assign them to a 7 day a
week calendar to allow them to start holiday on a week end. If there's not
ons already set-up go to Tools>Change Working Time.
You don't really need to assign resources for such a small schedule.
You can drop the date in the "Start" fields and tell each task when it will
start.
Hope this is what you're looking for.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top