K
KK
John can dig a hole twice as fast as Pete. I would like Project 2000 to
determine either John or Pete to work on a task "Dig the hole" but that
allocation to be made with the goal of minimizing overall project duration.
For instance, I would always prefer Joh to dig as he works twice as fast,
however, he has other tasks to do that are on the critical path so I get Pete
to do the digging that isn't on the critical path and so finish the project
as quickly as possible.
Can I do that?
determine either John or Pete to work on a task "Dig the hole" but that
allocation to be made with the goal of minimizing overall project duration.
For instance, I would always prefer Joh to dig as he works twice as fast,
however, he has other tasks to do that are on the critical path so I get Pete
to do the digging that isn't on the critical path and so finish the project
as quickly as possible.
Can I do that?