View Resource Assignments in PWA

J

jlbreyer

In the resource Center in PWA there is an action to View Resource
Assignments. There appear to be two choices: Gantt chart and timesheet. In
timesheet view, is there a way tohave it display Scheduled Work, or does it
only display Actual Work?
jlb
 
D

Dale Howard [MVP]

jib --

Select the Timesheet view, then click the View Options tab and select the
Show Schedule Work option. Hope this helps.
 
J

jlbreyer

Thanks, Dale. I could swear I looked there, but didn't see it. Must need
new glasses :)
 