For some reason I cannot get Project to just show the task list, without the
Gantt chart. I have tried all the view options, so what am I doing wrong? I
also want to create a PDF of the task list, with no Gantt chart. Thanks.
 
D

Dave

BobElmore said:
For some reason I cannot get Project to just show the task list, without the
Gantt chart. I have tried all the view options, so what am I doing wrong? I
also want to create a PDF of the task list, with no Gantt chart. Thanks.

To hide the Gantt chart, simply grab the leftmost edge of it and drag it
as far to the right as you can. If you want to view only the column
containing the names of the task you will have to hide or delete the
other columns. To do so, either click on the header and then press
delete or right click on the column header and click hide.

In order to create a PDF file then you will need to have a print driver
installed on your computer that creates that output. That particular
problem is outside Project itself and is more of a platform printing
problem for your machine.
 
D

Dale Howard [MVP]

Bob --

Why don't you do the following:

1. Click View - More Views
2. Select the Task Sheet view
3. Click the Apply button

Hope this helps.
 
B

BobElmore

Thanks for all your comments. I could have sworn I tried all the views, but
this worked.
 