K
KarenF
Hi,
We're working an 11 hour day - default working hours have been changed,
number of hours a day, hours a week and days a month have been changed, yet
if I schedule a 1-day task to start on say, today, it's finish date always
shows up as tomorrow. I've switched the dates views to show dates and times
and the task is starting at 09:00 one day and finishing at 09:00 the next day.
Does anyone have any ideas? This is a client's project database. Could it
be that he has subsequently changed the working hours? Even new tasks with
no predecessors (as he's been trying everything to experiment) are doing
this. I seem to vaguely recall a solution for this but can't remember the
details.
Many thanks,
Karen.
We're working an 11 hour day - default working hours have been changed,
number of hours a day, hours a week and days a month have been changed, yet
if I schedule a 1-day task to start on say, today, it's finish date always
shows up as tomorrow. I've switched the dates views to show dates and times
and the task is starting at 09:00 one day and finishing at 09:00 the next day.
Does anyone have any ideas? This is a client's project database. Could it
be that he has subsequently changed the working hours? Even new tasks with
no predecessors (as he's been trying everything to experiment) are doing
this. I seem to vaguely recall a solution for this but can't remember the
details.
Many thanks,
Karen.