A
Andrew K
Project Help says you create a link to an external task by Edit>Copy Cell in
the source file and then Paste Special>Paste Link in the target. The
resulting link doesn't display in Tools>Links between projects or in the
Predecessor and Successor fields. Also, if you start with Edit>Copy Task you
get an indelible constraint in the target.
Stover's method in Project Inside Out (2002) relies on being able to type
the path and task number of the external project. I find this is difficult
and error-prone if the files are on mapped network drives.
I've been using another method: 1) Insert the source and target projects
into a blank "master" project; 2) Select the source (predecessor) task, hold
down Ctrl, select the target (successor) task, and hit the Link Tasks icon.
Links created this way display both in Tools>Links between projects and also
in the Predecessor and Successor fields. Is this a legitimate method?
Please let me know your opinions and preferences.
the source file and then Paste Special>Paste Link in the target. The
resulting link doesn't display in Tools>Links between projects or in the
Predecessor and Successor fields. Also, if you start with Edit>Copy Task you
get an indelible constraint in the target.
Stover's method in Project Inside Out (2002) relies on being able to type
the path and task number of the external project. I find this is difficult
and error-prone if the files are on mapped network drives.
I've been using another method: 1) Insert the source and target projects
into a blank "master" project; 2) Select the source (predecessor) task, hold
down Ctrl, select the target (successor) task, and hit the Link Tasks icon.
Links created this way display both in Tools>Links between projects and also
in the Predecessor and Successor fields. Is this a legitimate method?
Please let me know your opinions and preferences.