R
RedHead
I would like to set the max units and assignments units based on
specific time intervals (i.e. 50% for Oct & Nov, 60% for Dec & Jan, 70%
for Feb & March, etc.... and so on.
I know on the resource usage view the resource availability from/to can
be entered. However, that is simply the max units the resource is
available during the intervals. However, this does not dynamically
make the resource assignment units match the max units during those
intervals.
The only way I see to accomplish this is to create a calendar with only
50%, 60%, 70% etc. available during those months and apply it as the
base calendar for the appropriate resources for which I want this to
apply.
I would think this would be fundamental capability of Project ? but
either it is not or I don't know how to do it.
Any advice would be apprepricated.
specific time intervals (i.e. 50% for Oct & Nov, 60% for Dec & Jan, 70%
for Feb & March, etc.... and so on.
I know on the resource usage view the resource availability from/to can
be entered. However, that is simply the max units the resource is
available during the intervals. However, this does not dynamically
make the resource assignment units match the max units during those
intervals.
The only way I see to accomplish this is to create a calendar with only
50%, 60%, 70% etc. available during those months and apply it as the
base calendar for the appropriate resources for which I want this to
apply.
I would think this would be fundamental capability of Project ? but
either it is not or I don't know how to do it.
Any advice would be apprepricated.