When I define a task by duration, the dates often do not match.

  • Thread starter Steve Czerwinski
  • Start date
S

Steve Czerwinski

I am a new user to microsoft project 2003. When i set a task's duration as
the constraint, the dates corresponding often do not match. This is a major
major problem and it is only thanks to an astute co-worker that the problem
was caught. Why is this happening?
 
J

Jack Dahlgren

Can you give an example?
You do know that the duration is in working days and does not include
weekends and holidays.

-Jack Dahlgren
 